Back to projects

Bus Shelter Acquisition 2018

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$49,754
Federal share50%

of $99.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 2, 2018
2018
Built

Approved 5 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jan 1, 2018(actual)
Construction end
Nov 15, 2018(actual)

Also in Laval

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51759 in the federal list. How to read these figures.