Back to projects

Electric vehicles and charging stations

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$16,909
Federal share50%

of $33.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 2, 2018
2018
Built

Approved 5 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jan 18, 2018(actual)
Construction end
Mar 31, 2018(actual)

Also in Laval