Purchase of four 30-foot diesel midibuses in 2019
Federal contribution
$884,994
Federal share50%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 3, 2018
201820192020
Built
Approved 7 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Société de transport de Saguenay (STS)
- Construction start
- Mar 9, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Also in Saguenay