Three 2019 hybrid buses
Federal contribution
$1.4M
$1,415,347
Federal share50%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 7, 2018
20182019
Built
Approved 8 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Société de transport de Trois-Rivières (STTR)
- Construction start
- May 25, 2018(actual)
- Construction end
- May 6, 2019(actual)
Also in Trois-Rivières
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51782 in the federal list. How to read these figures.