1 service and maintenance vehicle for the network

Trois-Rivières, Quebec

completePublic TransitPTIF
Federal contribution
$37,862
Federal share50%

of $75.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 7, 2018
2018
Built

Approved 8 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jul 31, 2018(actual)
Construction end
Aug 1, 2018(actual)