2017 Sanitary Sewer Study
Botwood, Newfoundland and Labrador
Federal contribution
$51,465
Federal share50%
of $102.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
201820192020
Built
Approved 23 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Botwood
- Construction start
- Oct 20, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start5 months earlyforecast Apr 1, 2018
- Construction end6 months lateforecast Oct 15, 2019
Also in Botwood
- Commonwealth Drive Watermain Replacement$809.7K
- Water Main Replacement & Associated Upgrades - Church Road$642.2K
- Water Main Replacement & Associated Upgrades - Sacrey's Road$358.7K
- 2017 Sanitary Sewer Outfall - Phase 1 Circular Road$249.8K
- Watermain Replacement Water Street Valley Road Intersection (2022)$230.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51806 in the federal list. How to read these figures.