Waste Water Treatment Plant Standby Generator Design and Approvals
South Bruce Peninsula, Ontario
Federal contribution
$20,000
Federal share50%
of $40.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 8, 2019
2019
Built
Approved 10 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Town of South Bruce Peninsula
- Construction start
- Jan 28, 2018(actual)
- Construction end
- Jun 26, 2019(actual)
Against the original forecast
- Construction start17 months lateforecast Sep 12, 2016
- Construction end7 months lateforecast Nov 30, 2018
Also in South Bruce Peninsula
- Mary Street Water, Wastewater and Storm Sewer Replacement$1.1M
- Gould Street and Pengally Avenue Watermain Replacement$1.1M
- Design Upgrades for Sewage Pump Station #1 located at 524 Taylor Street, Wiarton$85.0K
- Bluewater Park Trail Enhancement$80.0K
- Gravity Sewer Inflow and Infiltration Investigation in Wiarton - work will occur throughout Wiarton, but will concentrate on Berford Street between Frank Street and Division Street$78.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51874 in the federal list. How to read these figures.