Installation of Sentinel Monitoring Well to ensure the usefull life of the asset identified as Production Well #1 is realized.

Penetanguishene, Ontario

completeDrinking WaterCWWF
Federal contribution
$10,000
Federal share50%

of $20.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 8, 2019
2019
Built

Approved 10 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Penetanguishene
Construction start
Sep 10, 2018(actual)
Construction end
Oct 28, 2018(actual)

Against the original forecast

  • Construction start11 months lateforecast Sep 25, 2017
  • Construction end9 months lateforecast Jan 30, 2018