Engineering Design for the Installation of a Dechlorinating System
Federal contribution
$31,784
Federal share42%
of $75.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 8, 2019
20192020
Built
Approved 10 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Penetanguishene
- Construction start
- Oct 1, 2018(actual)
- Construction end
- Aug 7, 2020(actual)
Against the original forecast
- Construction start11 months lateforecast Nov 1, 2017
- Construction end5 months lateforecast Feb 28, 2020