Frozen Water Services Lowering Program- Phase 2 Georgetown

Halton, Ontario

completeDrinking WaterCWWF
Federal contribution
$679,500
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 8, 2019
201820192020
Built

Approved 10 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 1, 2018(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast Aug 1, 2017
  • Construction end9 months lateforecast Jun 30, 2019