Frozen Water Services Lowering Program- Phase 2 Georgetown
Federal contribution
$679,500
Federal share50%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 8, 2019
201820192020
Built
Approved 10 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Regional Municipality of Halton
- Construction start
- Jan 1, 2018(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast Aug 1, 2017
- Construction end9 months lateforecast Jun 30, 2019
Also in Halton
- Second Feedermain to the Washburn Reservoir and Booster Station$17.3M
- Crawford Lake Visitor Centre Retrofit$2.4M
- Frozen Water Services Lowering Program- Phase 3, 4, 5 Acton, Oakville and Burlington$1.8M
- Technical Standards and Safety Authority (TSSA) Upgrades at Five Pumping Stations$520.0K
- TSSA Upgrades at Four Pumping Stations$280.0K