Frozen Water Services Lowering Program- Phase 3, 4, 5 Acton, Oakville and Burlington
Federal contribution
$1.8M
$1,823,358
Federal share27%
of $6.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 8, 2019
20192020
Built
Approved 10 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Regional Municipality of Halton
- Construction start
- Apr 1, 2018(actual)
- Construction end
- Sep 30, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 1, 2017
Also in Halton
- Second Feedermain to the Washburn Reservoir and Booster Station$17.3M
- Crawford Lake Visitor Centre Retrofit$2.4M
- Frozen Water Services Lowering Program- Phase 2 Georgetown$679.5K
- Technical Standards and Safety Authority (TSSA) Upgrades at Five Pumping Stations$520.0K
- TSSA Upgrades at Four Pumping Stations$280.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51880 in the federal list. How to read these figures.