Improvement of tourist reception facilities in Bromont
Federal contribution
$18,200
Federal share33%
of $54.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 2, 2018
20182019
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Bromont
- Construction start
- Oct 15, 2018(actual)
- Construction end
- Apr 25, 2019(actual)
Against the original forecast
- Construction start10 months lateforecast Nov 30, 2017
- Construction end10 months lateforecast Jun 15, 2018
Also in Bromont
- Reconstruction of Urban Infrastructure - Sheffort Street$1.2M
- Water Systems Upgrade$820.3K
- Program for the renewal of drinking water and wastewater pipes$327.2K
- Sewage collection changes in Deux-Montagnes, Montcalm and Richmond streets sectors$259.0K
- Program for the renewal of drinking water and wastewater pipes$169.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51904 in the federal list. How to read these figures.