Canada Summit Centre and Park Drive Safety Improvements
Federal contribution
$38,043
Federal share37%
of $102.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 12, 2019
20182019
Built
Approved 11 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the Town of Huntsville
- Construction start
- Apr 30, 2017(actual)
- Construction end
- Oct 30, 2017(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 2, 2017
- Construction end2 months earlyforecast Jan 2, 2018
Also in Huntsville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51931 in the federal list. How to read these figures.