Renovation of the Petites Franciscaines de Marie complex to accommodate the Charlevoix-Ouest Television station

Baie-Saint-Paul, Quebec

completeCultureSCF
Federal contribution
$6,541
Federal share33%

of $19.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 7, 2018
20192020
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Baie-Saint-Paul
Construction start
May 22, 2018(actual)
Construction end
Feb 22, 2020(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 1, 2018
  • Construction end20 months lateforecast Jul 1, 2018