Back to projects

Société de transport de Laval website

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$163,878
Federal share50%

of $327.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 11, 2018
201920202021
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Mar 1, 2018(actual)
Construction end
Mar 31, 2021(actual)