Replacement of bus shelters in 2019

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$150,000
Federal share50%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 11, 2018
20192020
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 1, 2019(actual)
Construction end
Mar 18, 2020(actual)