Increase in the number of vehicles - On-board bus equipment 2019

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$149,658
Federal share50%

of $299.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 11, 2018
2019
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 27, 2019(actual)
Construction end
Nov 29, 2019(actual)