Back to projects

Driving simulator

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$130,925
Federal share50%

of $261.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 11, 2018
20192020
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
May 3, 2019(actual)
Construction end
Feb 27, 2020(actual)