Back to projects

Gradual deployment - Electric bicycles

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$30,842
Federal share50%

of $61.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 11, 2018
2019
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
May 6, 2019(actual)
Construction end
Nov 3, 2019(actual)

Also in Laval