Park-and-Ride lot with miniterminal, Chicoutimi, south sector
Federal contribution
$1.2M
$1,234,585
Federal share50%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 3, 2018
2019202020212022
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Société de transport de Saguenay (STS)
- Construction start
- Mar 31, 2019(actual)
- Construction end
- Sep 30, 2022(actual)
Also in Saguenay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52034 in the federal list. How to read these figures.