Visart Street - Watermain Renewal and Sewer Separation
Federal contribution
$187,411
Federal share33%
of $562.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 10, 2018
20192020
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Saint John
- Construction start
- May 8, 2018(actual)
- Construction end
- Dec 17, 2019(actual)
Against the original forecast
- Construction end17 months lateforecast Jul 6, 2018
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52066 in the federal list. How to read these figures.