Replace Existing Buses
Federal contribution
$39,843
Federal share47%
of $85.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 13, 2018
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Sault Ste. Marie
- Construction start
- Jan 3, 2018(actual)
- Construction end
- Sep 3, 2019(actual)
Against the original forecast
- Construction end7 months earlyforecast Mar 31, 2020
Also in Sault Ste. Marie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52067 in the federal list. How to read these figures.