Brandon - Transit Terminal Safety Fencing

Brandon, Manitoba

completePublic TransitPTIF
Federal contribution
$10,502
Federal share14%

of $75.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2019
2019
Built

Approved 11 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Brandon
Construction start
Jul 23, 2019(actual)
Construction end
Oct 31, 2019(actual)

Against the original forecast

  • Construction start2 months earlyforecast Sep 30, 2019
  • Construction end4 weeks lateforecast Oct 1, 2019

Also in Brandon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52162 in the federal list. How to read these figures.