Brandon - Fiber Optic Connectivity for Transit Station
Federal contribution
$28,253
Federal share19%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2019
2019
Built
Approved 11 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Brandon
- Construction start
- Nov 15, 2018(actual)
- Construction end
- Aug 19, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 1, 2018
- Construction end3 weeks lateforecast Jul 31, 2019
Also in Brandon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52163 in the federal list. How to read these figures.