Watermain Replacement, Phase 3

Burgeo, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$158,826
Federal share33%

of $476.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2018
2019
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Burgeo
Construction start
Aug 18, 2019(actual)
Construction end
Nov 15, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 1, 2019
  • Construction end7 weeks earlyforecast Dec 31, 2019

Also in Burgeo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52177 in the federal list. How to read these figures.