Water Main Replacement Phase 6

Burgeo, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$490,992
Federal share40%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
20212022
Built

Approved 8 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Burgeo
Construction start
Sep 5, 2021(actual)
Construction end
Aug 3, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast May 25, 2021
  • Construction end4 months lateforecast Mar 31, 2022