Back to projects

Watermain Replacement - Phase 2

Burgeo, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$453,417
Federal share50%

of $906.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Burgeo
Construction start
Sep 6, 2017(actual)
Construction end
Jul 31, 2018(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 1, 2017
  • Construction end5 months earlyforecast Dec 31, 2018

Also in Burgeo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46966 in the federal list. How to read these figures.