Sewer Infrastructure Upgrades
Hopedale, Newfoundland and Labrador
Federal contribution
$273,534
Federal share33%
of $820.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2018
20192020
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Inuit Community Government of Hopedale
- Construction start
- Oct 1, 2018(actual)
- Construction end
- Apr 28, 2020(actual)
Against the original forecast
- Construction start7 months earlyforecast May 1, 2019
- Construction end4 months lateforecast Dec 30, 2019
Also in Hopedale
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52178 in the federal list. How to read these figures.