Sewer Infrastructure Upgrades

Hopedale, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$273,534
Federal share33%

of $820.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2018
20192020
Built

Approved 8 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Oct 1, 2018(actual)
Construction end
Apr 28, 2020(actual)

Against the original forecast

  • Construction start7 months earlyforecast May 1, 2019
  • Construction end4 months lateforecast Dec 30, 2019