Relocate American Pond Intake Chamber

Hopedale, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$303,245
Federal share40%

of $758.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
2023202420252026
Built

Approved 3.2 years before the announcement.

Program
Green Infrastructure Stream
Construction start
Aug 12, 2024(actual)
Construction end
May 3, 2025(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2024
  • Construction end5 months lateforecast Nov 29, 2024

Also in Hopedale

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65137 in the federal list. How to read these figures.