Water and Sewer Services to Wharf Area

Hopedale, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$235,322
Federal share40%

of $588.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2022
20222023
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jun 19, 2023(actual)
Construction end
Aug 21, 2023(actual)

Against the original forecast

  • Construction end6 weeks earlyforecast Sep 30, 2023