Lincoln Road Phase II
Grand Falls-Windsor, Newfoundland and Labrador
Federal contribution
$302,185
Federal share33%
of $906.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2018
2019
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Grand Falls-Windsor
- Construction start
- Aug 31, 2018(actual)
- Construction end
- Nov 21, 2019(actual)
Against the original forecast
- Construction start7 months earlyforecast Apr 1, 2019
- Construction end2 years earlyforecast Nov 30, 2021
Also in Grand Falls-Windsor