2018 Water System Improvements
Upper Island Cove, Newfoundland and Labrador
Federal contribution
$58,569
Federal share27%
of $217.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2018
201920202021
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Upper Island Cove
- Construction start
- Sep 2, 2019(actual)
- Construction end
- Feb 22, 2021(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 12, 2019
- Construction end5 weeks earlyforecast Mar 31, 2021