Upper Island Cove Water System Improvements - Janes Lane and Cranes Lane
Upper Island Cove, Newfoundland and Labrador
Federal contribution
$164,662
Federal share40%
of $411.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20222023
Built
Approved 5 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Upper Island Cove
- Construction start
- Aug 7, 2023(actual)
- Construction end
- Aug 31, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2023
- Construction end2 months earlyforecast Oct 31, 2023
Also in Upper Island Cove
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61066 in the federal list. How to read these figures.