Waterline Replacements - Mountain Road and Lundrigan's Lane
Upper Island Cove, Newfoundland and Labrador
Federal contribution
$134,008
Federal share40%
of $335.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 5, 2024
202320242025
Built
Approved 2.3 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Upper Island Cove
- Construction start
- Nov 1, 2024(actual)
- Construction end
- Dec 12, 2024(actual)
Against the original forecast
- Construction start8 weeks lateforecast Sep 6, 2024
Also in Upper Island Cove
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65213 in the federal list. How to read these figures.