High Street Water, Sewer and Storm Upgrade - Phase 1
Deer Lake, Newfoundland and Labrador
Federal contribution
$453,344
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2018
2019
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Deer Lake
- Construction start
- May 7, 2019(actual)
- Construction end
- Sep 1, 2019(actual)
Against the original forecast
- Construction start3 weeks earlyforecast May 30, 2019
- Construction end15 months earlyforecast Nov 30, 2020
Also in Deer Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52226 in the federal list. How to read these figures.