Back to projects

Completion of Transmission Main and Water Tank

Campbellton, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$415,062
Federal share32%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2018
20192020202120222023
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Campbellton
Construction start
Jul 27, 2020(actual)
Construction end
Dec 27, 2022(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Aug 15, 2020
  • Construction end4 weeks lateforecast Nov 30, 2022

Also in Campbellton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52235 in the federal list. How to read these figures.