Bob Clark Drive Upgrading (Phase 2)

Campbellton, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$143,635
Federal share33%

of $430.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2024
20232024
Built

Approved 19 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Campbellton
Construction start
Sep 25, 2023(actual)
Construction end
Oct 27, 2023(actual)

Against the original forecast

  • Construction start7 months earlyforecast May 2, 2024
  • Construction end8 months earlyforecast Jun 30, 2024