Waterline extension on Road to the Isles and Kingman/Decker Drive
Campbellton, Newfoundland and Labrador
Federal contribution
$253,886
Federal share40%
of $634.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
20242025
Built
Approved 21 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Campbellton
- Construction start
- May 26, 2025(actual)
- Construction end
- Aug 20, 2025(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 15, 2025
Also in Campbellton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67396 in the federal list. How to read these figures.