Water System Sampling Stations

Riverside-Albert, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$6,951
Federal share31%

of $22.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2018
2019
Built

Approved 5 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Riverside-Albert
Construction start
Jun 15, 2019(actual)
Construction end
Jul 5, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast May 1, 2018
  • Construction end12 months lateforecast Jun 30, 2018