Expansion to water infrastructure to reduce risk & impacts of drought MBQ Territory
Mohawks of the Bay of Quinte, Ontario
Federal contribution
$30.1M
$30,093,216
Federal share75%
of $40.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 20, 2019
20202021202220232024
Built
Approved 4 weeks before the announcement.
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- Mohawks of the Bay of Quinte
- Construction start
- Jan 11, 2021(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start8 months lateforecast May 1, 2020
- Construction end4 weeks earlyforecast Dec 31, 2023
Also in Mohawks of the Bay of Quinte
- Watermain Extension on Old Highway 2, Bells Road and North Street$3.5M
- Reconstruction of a Section of York Road and Rehabilitation of the Mud Creek Bridge$3.3M
- Bayshore Road Wastewater Pumping Station Upgrade$937.7K
- Huron Brant Pumping Station Improvements$77.2K
- Replacement and upgrade to the existing analog water meters with new digital remote technology$29.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52900 in the federal list. How to read these figures.