Huron Brant Pumping Station Improvements

Mohawks of the Bay of Quinte, Ontario

completeWastewaterCWWF
Federal contribution
$77,207
Federal share43%

of $178.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 10, 2017
ApprovedMar 27, 2018
2018
Built

Approved 6 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Feb 19, 2018(actual)
Construction end
Aug 24, 2018(actual)

Against the original forecast

  • Construction start10 months lateforecast May 1, 2017
  • Construction end5 months lateforecast Mar 31, 2018

Also in Mohawks of the Bay of Quinte

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51358 in the federal list. How to read these figures.