Bayshore Road Wastewater Pumping Station Upgrade
Mohawks of the Bay of Quinte, Ontario
Federal contribution
$937,673
Federal share75%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 20, 2020
2021202220232024
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Mohawks of the Bay of Quinte
- Construction start
- Dec 23, 2021(actual)
- Construction end
- Nov 27, 2023(actual)
Against the original forecast
- Construction end4 months lateforecast Jul 30, 2023
Also in Mohawks of the Bay of Quinte
- Expansion to water infrastructure to reduce risk & impacts of drought MBQ Territory$30.1M
- Watermain Extension on Old Highway 2, Bells Road and North Street$3.5M
- Reconstruction of a Section of York Road and Rehabilitation of the Mud Creek Bridge$3.3M
- Huron Brant Pumping Station Improvements$77.2K
- Replacement and upgrade to the existing analog water meters with new digital remote technology$29.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57301 in the federal list. How to read these figures.