West Hants Arena and Soccer Field

West Hants, Nova Scotia

completeRecreationCCRIS
Federal contribution
$4.4M
$4,430,400
Federal share40%

of $11.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 20, 2018
20192020
Built

Approved 5 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Jul 18, 2019(actual)
Construction end
Oct 29, 2020(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2019
  • Construction end4 weeks lateforecast Sep 30, 2020

Also in West Hants

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52968 in the federal list. How to read these figures.