West Hants Arena and Soccer Field
Federal contribution
$4.4M
$4,430,400
Federal share40%
of $11.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 20, 2018
20192020
Built
Approved 5 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of the District of West Hants
- Construction start
- Jul 18, 2019(actual)
- Construction end
- Oct 29, 2020(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2019
- Construction end4 weeks lateforecast Sep 30, 2020
Also in West Hants
- West Hants Regional Municipality - College Road and Nesbitt Street Infrastructure Renewal$1.6M
- Retrofit of Hants County Exhibition Arena Upgrade$850.0K
- Hantsport - Holmes Hill Rehabilitation$843.2K
- School Street rehabilitation$679.2K
- Municipality of the District of West Hants - Hantsport Infrastructure Rehabilitation - Main Street South and Prince Street$484.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52968 in the federal list. How to read these figures.