Hantsport - Holmes Hill Rehabilitation
Federal contribution
$843,224
Federal share50%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of the District of West Hants
- Construction start
- Oct 4, 2016(actual)
- Construction end
- Jun 22, 2017(actual)
Against the original forecast
- Construction end9 months earlyforecast Mar 31, 2018
Also in West Hants
- West Hants Arena and Soccer Field$4.4M
- West Hants Regional Municipality - College Road and Nesbitt Street Infrastructure Renewal$1.6M
- Retrofit of Hants County Exhibition Arena Upgrade$850.0K
- School Street rehabilitation$679.2K
- Municipality of the District of West Hants - Hantsport Infrastructure Rehabilitation - Main Street South and Prince Street$484.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47208 in the federal list. How to read these figures.