Back to projects

West Hants Regional Municipality - College Road and Nesbitt Street Infrastructure Renewal

West Hants, Nova Scotia

completeDrinking WaterGIS
Federal contribution
$1.6M
$1,647,600
Federal share25%

of $6.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 15, 2023
202320242025
Built

Approved 9 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 10, 2023(actual)
Construction end
Sep 30, 2025(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 12, 2023
  • Construction end3 months earlyforecast Dec 31, 2025

Also in West Hants