Teslin Public Works Facilities

Teslin, Yukon

completeAdministration, Emergency and Public WorksSCF
Federal contribution
$300,000
Federal share75%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2019
20192020202120222023
Built

Approved 7 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Teslin
Construction start
May 13, 2020(actual)
Construction end
Jan 9, 2023(actual)

Against the original forecast

  • Construction end10 months earlyforecast Oct 31, 2023