Watson Lake Administrative Building Retrofit
Federal contribution
$2.1M
$2,062,500
Federal share75%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 24, 2020
201920202021
Built
Approved 20 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Watson Lake
- Construction start
- Sep 18, 2019(actual)
- Construction end
- Jun 9, 2021(actual)
Against the original forecast
- Construction start7 weeks lateforecast Aug 1, 2019
- Construction end3 weeks earlyforecast Jun 30, 2021
Also in Watson Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52986 in the federal list. How to read these figures.