Highway 1 / Douglas Street Southbound Bus Lane (Burnside Bridges - Tolmie)
Federal contribution
$3.3M
$3,332,159
Federal share40%
of $8.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 6, 2019
20202021
Built
Approved 2 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- British Columbia Ministry of Transportation and Infrastructure
- Construction start
- Jun 19, 2019(actual)
- Construction end
- Apr 15, 2021(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2019
- Construction end12 months lateforecast Mar 31, 2020
Also in Saanich
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53156 in the federal list. How to read these figures.