Highway 1 / Douglas Street Southbound Bus Lane (Burnside Bridges - Tolmie)

Saanich, British Columbia

completePublic TransitPTIS
Federal contribution
$3.3M
$3,332,159
Federal share40%

of $8.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2019
20202021
Built

Approved 2 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Jun 19, 2019(actual)
Construction end
Apr 15, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2019
  • Construction end12 months lateforecast Mar 31, 2020