Back to projects

Carmacks Recreation Centre Water Treatment System

Carmacks, Yukon

completeWastewaterGIS
Federal contribution
$463,500
Federal share75%

of $618.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 2, 2019
20202021
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Carmacks
Construction start
May 23, 2019(actual)
Construction end
Apr 12, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 1, 2019
  • Construction end7 weeks earlyforecast May 31, 2021

Also in Carmacks

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53563 in the federal list. How to read these figures.