Carmacks Recreation Centre Water Treatment System
Federal contribution
$463,500
Federal share75%
of $618.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 2, 2019
20202021
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Carmacks
- Construction start
- May 23, 2019(actual)
- Construction end
- Apr 12, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 1, 2019
- Construction end7 weeks earlyforecast May 31, 2021
Also in Carmacks
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53563 in the federal list. How to read these figures.