FortWhyte Forever
Federal contribution
$1.3M
$1,291,312
Federal share33%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 2, 2019
20202021
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- The FortWhyte Foundation Inc.
- Construction start
- May 5, 2020(actual)
- Construction end
- Jul 16, 2021(actual)
Against the original forecast
- Construction start6 months lateforecast Nov 1, 2019
- Construction end2.7 years earlyforecast Mar 31, 2024